AS 7 Accounting for construction contracts:
Introduction:
This AS is formed
to give the contractors a proper method of accounting to record their
transaction in the financial statements. Earlier the contractor were facing
difficulty regarding the recording of revenue in their financial statement
cause as we know construction work takes long time to construct, normally more
than 1 year, this created confusing situation that whether to record the
transaction in the year in which the construction get finished or before, and
if they recognized the revenue before; that would be the violation of prudence
principal. If they recorded the revenue in the year of completion then what
about those past years the contractor spent to make the work? To remove these
confusion this AS is formed.
Explanation:
Meaning of
construction contracts: it means the contract taken by an enterprise
(contractor) to construct the assets. These assets may be single or the
combination of inter dependent or interrelated assets. Example of single
asset—road, ship, pipeline, tunnel, etc, and examples of interrelated is –
complex pieces of plants and equipments
Included in definition: for the purpose of this standard,
construction contract include-
1)
Contracts
for rendering Services directly related to the construction like service of
architecture, and
2)
Contract
for destruction of assets.
Additional assets:
If it is required to construct additional asset at the
option of customer, this asset will be regarded as separate contract when, a)
the price of this asset can be negotiated separately and b) it is different in
design, technology or function.
Number of assets:
When construction contract contain number of assets, each
assets will be regarded as separate assets when cost and revenue of each asset
can be separately identifiable, proposal of each asset are submitted
separately, and the negotiation of each asset is possible.
Contract revenue:
Contract revenue include initial amount of contract plus
or minus, variation in contract..variation occurs in many cases like claims of
contractor, penalty charge by customer for late work, or increase of other
inter related assets or modification in existing asset etc etc.
Contract cost:
Contract cost include a) direct cost related directly to
construction like labor cost, material cost, depreciation of plant and
equipment cost, etc.. b) Allocated cost like insurance, and borrowing cost related to construction…c) specific cost like
general and administrative costs that are reimbursable.
Cost not included under construction cost:
a)
General
and administrative cost that are non reimbursable.
b)
Selling
cost
c)
Research
and Development cost that are non reimbursable
d)
Depreciation
of idle machinery.
TYPES OF CONTRACT:
There are two types of contracts 1) fixed price contracts
and 2) cost plus contracts.
Fixed price contract: in this contract, the price is
fixed before commencing the construction, and in some cases enterprise requires
its customer to pay extra price as cost escalation.
Cost plus contracts: in this contract, the customer
reimbursed the cost of the construction and in addition to this, the fee of the
contractor (determined as a percentage of that cost) is also paid by the
customer.
Methods of accounting of construction contract:
PERCENTAGE COMPLETION METHOD:
This method says an enterprise under construction
contract can record the revenue and its corresponding cost annually, in its
books, in proportionate to the progress of the work during the year.
For example, 30% of the construction of bridge is
completed during the year. Contract price was 10 crore, cost incurred during
the year is 1.3 crore. According to this method, 3 crore will be the revenue
and 1.7 crore(3.00-1.3) will be the profit of that year.
This AS allows the enterprise to apply this method only
when it’s possible to estimate the final outcome of the contract.
In case of fixed price contract the outcome can be
estimated reliably when:
The total contract revenue, expected cost to complete
that contract, and the stage of completion of contract can be measured reliably
and it’s probable that the economic benefit will flow to the enterprise.
Outcome of cost plus contract can be estimated reliably
when:
It’s probable that the economic benefit will flow from
that contract and the contract cost require to complete the contract can be
measured reliably
If the outcome can’t be estimated the PCM will not be
applicable and in that case:
1)
Revenue
should be recognized only to the extent the cost is incurred,
2)
Contract
cost should be recognized as expense.
Expectation
of losses:
At certain point of construction if realized that we will
have loss in the future the expected loss will be recorded immediately in the
profit and loss account.
Suppose— contract price = 10 crore, at the end of the
year cost incurred is 4 crore, at that point, cost required to complete the
whole construction was estimated 8 crore by contractor. Now contractor can
determine the total cost which is 4+8= 12 crore, he can determine from this;
the percentage of work completed which is 4/12*100=33.33% now he can easily
determine the revenue of that work during the year which is 10*33.33/100=3.33
crore. Now the contractor can see that cost during the year=4 crore, revenue
during the year=3.33 crore so loss during the year=0.67, but he can also see
that the future loss will be (2 -0.67) which is 1.33 crore, this AS advise the
contractor to recognize this future loss of 1.33 immediately in the books of
account. After doing all these work the scenario of the profit and loss account
during the year will be : contract price (as revenue)=3.33 crore,
Contract cost =4 crore,
Provision for loss=1.33 crore,
Total loss of the profit and loss account during the year=2
crore.
Here It’s to be noted that in cost plus method the above
provision will not be apply because the contractor get the fee above cost price
so no chance of expected loss.
Change in estimates—if there is a change in estimates it
will be treated as per AS 5 That is, change in estimates will be recognize in
the financial statement in the year in which change takes place.
DISCLOSURE:
A)
An
enterprise required to disclose;
1)
Amount
of contract revenue recognized as revenue during the year,
2)
Method
used to recognize the revenue,
3)
The
method used to determine the stage of completion of contract,
B)
For
contract in progress:
1)
Aggregate
amount of cost incurred and recognized profit upto the reporting date.
2)
Amount
of advance received,
3)
Amount
of retention.
C)
Gross
amount due from or due to customer for contract work.
e)
Contingencies
in relation to penalty cost, or possible loss.
EXCEPTION OF
AS 7:
The revised
AS 7 will not be applicable for the accounting of new housing projects
undertaken by the company on or after 1/4/2013.
The AS 7,
will also not applicable for real estate developers, for them AS 9 will be
applicable.
These was all about this Accounting standard; hope you all like it.
Thanks for one marvelous posting! I enjoyed reading it; you are a great
ReplyDeleteAuthor. I suggest Customer Reconciliation | Fixed Assets Audit | CFA Audit
Hi admin, I have read your post. It was really awesome post. Keep in blogging..... Duplicate Payment
ReplyDeleteProfit Recovery
Continuous Monitoring